Technical study · Engineering & Design

Solar and Battery for a Food Processing Plant

Interval data, tariff and switchboard analysis to size behind-the-meter solar and a battery for a food plant paying about $310,000 a year in demand charges, including the battery risk most proposals miss.

Aerial view of a factory roof covered in solar panels beside a loading dock

What the client needed

A food processing plant in South East Queensland uses about 12 GWh of electricity a year, with refrigeration and process loads that peak in the late afternoon. Network demand charges had become one of the largest lines on its power bill.

The question they needed answered: What size of solar and battery makes financial sense for the site, and how much will it really save?

  • 4.4 yearssimple payback on 2 MWp of solar
  • 1.8 to 0.8 MWpeak demand with a 1 MW / 4 MWh battery
  • ~36%chance a month's demand saving is lost to one missed peak day

What we did

  • Analysed 12 months of 30-minute interval data against the site's network demand tariff.
  • Modelled rooftop and carpark solar, and batteries from 0.5 to 2 MW, dispatched to target the network peak window.
  • Checked roof structure, switchboard capacity, protection and connection requirements.
  • Compared solar-only and solar-plus-battery options on capital cost, savings and payback.

What we found

Each kVA of peak demand costs nearly $14 a month under the site's tariff. The late-afternoon peak alone was setting about $310,000 a year in demand charges.

2 MWp of solar produces about 2.9 GWh a year, all used on site, for around $500,000 a year in savings.

A battery discharging from 4pm to 9pm cuts peak demand from about 1.8 MW to 0.8 MW, worth around $165,000 a year. On its own it pays back slowly, but it also backs up critical refrigeration.

The constraint was the main switchboard, not the roof. It needs a new incoming section to take the battery inverter.

Demand charges are set by the worst half-hour each month. At 98% battery availability over about 22 peak days, there's roughly a 36% chance of missing at least one day, which can cut the expected demand saving by about a third.

Line chart of a typical summer weekday showing site load, solar generation and grid import after solar and battery
A typical summer weekday: site load before, solar generation, and grid import with solar and the battery covering the network peak window.

What we recommended

  • Install 2 MWp of solar now.
  • If the battery goes ahead, base its performance guarantee on monthly peak demand achieved, not battery uptime.
  • Hold a reserve state of charge before the peak window, and use load and weather forecasts to schedule the battery.
  • Design the switchboard upgrade now either way, and re-run the numbers each year as tariffs change.

Key assumptions

Energex network tariff 7200 (FY2026-27) at $13.91/kVA/month peak demand. Solar yield 1,450 kWh/kWp a year, avoided energy cost around $0.16/kWh. Solar around $1.05/W and battery around $550/kWh installed.

Related work

Talk to our engineers

Tell us what you're working on, and one of the people below will get back to you.

Talk directly to

  • Andrew LelliottOperations Director
  • Alistair WardropeTechnical Director

Want to join us? We're always keen to hear from engineers who value strong fundamentals and real delivery experience.

Careers at Amarna